Dubai Investment Real Estate

Asayel Avenue

Construction Updates

March 2026 Edition

Progress Overview

Superstructure works are advancing steadily across all four zones, with concrete slabs cast up to the 3rd and 4th floor levels. Block work has commenced from the basement through to the second floor, while plaster and MEP first-fix activities are now active on the first floor.

01

Superstructure Rising

Slabs cast up to the 4th floor across all four construction zones

02

Block Work Underway

Block work active from basement through to second floor level

03

MEP First-Fix Initiated

MEP first-fix works started on the first floor, final fix at basement
Overall
Completion
0%

Construction Progress

Site Mobilization
100%
Enabling Works
100%
Piling & Foundations
100%
Substructure
100%
Superstructure
60%
Internal Works
6%
External Envelope
1%
Building Services
0.1%
Internal Finishes
0.1%
External Works
0.1%
Infrastructure
0.1%

Project Progress Summary

Superstructure Advancing

Zones 1 and 3 reached 3rd slab level; Zone 2 achieved 4th slab; Zone 4 reached third floor

Block Work & Plaster Active

Block work running from basement to second floor; plastering initiated on the first floor

MEP First-Fix Underway

MEP first-fix active on the first floor; high-level final fix commenced at basement level

External Envelope Initiated

External envelope works have commenced at 1%, marking the beginning of facade activities on site

What's Next

01

Continue superstructure casting to upper floor levels across all zones

02

Extend block work and plaster works progressively to higher floors

03

Progress MEP installations floor by floor in line with superstructure advance

Q4 2027

Project Handover

Days
Hours
Minutes
Construction activities are progressing in line with the development schedule, with key milestones actively being achieved on site. We will continue to share regular updates to keep all investors informed of ongoing construction progress. All completion percentages and timelines are indicative and may be subject to change based on site conditions and construction requirements.